Seismic mitigation retrofit and life-cycle replacements project at the Economic and Social Commission for Asia and the Pacific premises in Bangkok : report of the Secretary-General
2023
Formats
| Format | |
|---|---|
| BibTeX | |
| MARCXML | |
| TextMARC | |
| MARC | |
| DublinCore | |
| EndNote | |
| NLM | |
| RefWorks | |
| RIS |
Files
Details
Symbol
A/78/346
Title
Seismic mitigation retrofit and life-cycle replacements project at the Economic and Social Commission for Asia and the Pacific premises in Bangkok : report of the Secretary-General
Access
Authors
Agenda information
Date
[New York] : UN, 8 Sept. 2023
Description
29 p. : graphs, tables
Notes
Annexes (p. 24-29): 1. Revised cost plan -- 2. Evolution of resources in cost plans -- 3. A. Monthly expenditure from project inception to 31 July 2023, B. Total project expenditure by category as at 31 July 2023 -- 4. Use of the escalation and contingency provision (spent and earmarked).
Submitted pursuant to section 7 of General Assembly 77/263 A; provides update since the previous report of the Secretary-General (A/77/330).
Submitted pursuant to section 7 of General Assembly 77/263 A; provides update since the previous report of the Secretary-General (A/77/330).