Progress in the construction of new office facilities at the Economic Commission for Africa in Addis Ababa, and update on the renovation of conference facilities, including Africa Hall : report of the Secretary-General
2016
Formats
| Format | |
|---|---|
| BibTeX | |
| MARCXML | |
| TextMARC | |
| MARC | |
| DublinCore | |
| EndNote | |
| NLM | |
| RefWorks | |
| RIS |
Files
Details
Symbol
A/71/370
Title
Progress in the construction of new office facilities at the Economic Commission for Africa in Addis Ababa, and update on the renovation of conference facilities, including Africa Hall : report of the Secretary-General
Access
Authors
Date
[New York] : UN, 31 Aug. 2016
Description
24 p. : chart, graphs, tables
Notes
Annexes (p. 22-24): 1. Project cost for the construction of new office facilities at the Economic Commission for Africa -- 2. Project governance structure -- 3. Project cost plan for the renovation of the Africa Hall Building at the Economic Commission for Africa: 2015-2021.
Submitted pursuant to section I of General Assembly resolution 70/248 A; provides an update since the issuance of the previous report of the Secretary-General (A/70/363 and Corr.1).
Submitted pursuant to section I of General Assembly resolution 70/248 A; provides an update since the issuance of the previous report of the Secretary-General (A/70/363 and Corr.1).