Progress in the construction of new office facilities at the Economic Commission for Africa in Addis Ababa, and update on the renovation of conference facilities, including Africa Hall : report of the Secretary-General
2015
Files
Notice détaillée
SymboleA/70/363
TitreProgress in the construction of new office facilities at the Economic Commission for Africa in Addis Ababa, and update on the renovation of conference facilities, including Africa Hall : report of the Secretary-General
AccèsEnglish: A_70_363-EN - PDF ; Español: A_70_363-ES - PDF ; Français: A_70_363-FR - PDF ; Русский: A_70_363-RU - PDF ; العربية: A_70_363-AR - PDF ; 中文: A_70_363-ZH - PDF ;
AuteursUN. Secretary-General
Ordre du jour
A/70/251 134 Proposed programme budget for the biennium 2016-2017. UN--BUDGET (2016-2017)
Date[New York] : UN, 8 Sept. 2015
Description
29 p. : graphs, tables
Notes
Annexes (p. 24-29): 1. Substantially completed road, sidewalk, ramp and parking ancillary projects at the new office facilities at the Economic Commission for Africa (Zambezi Building) -- July 2015 -- 2. Project cost for the construction of new office facilities at the Economic Commission for Africa -- 3. Africa Hall renovation project governance structure -- 4. Roles of the remaining positions of the dedicated project management team and project support -- 5. Project cost plan for the proposed renovation of the Africa Hall Building at the Economic Commission for Africa, by year.
Submitted pursuant to section I of General Assembly resolution 63/263; provides an update since the issuance of the previous report of the Secretary-General (A/69/359).
Submitted pursuant to section I of General Assembly resolution 63/263; provides an update since the issuance of the previous report of the Secretary-General (A/69/359).