Progress on the replacement of office blocks A-J at the United Nations Office at Nairobi : report of the Secretary-General
2023
Files
تفصيلات التسجيلة (السجل)
رمز / رقم الاستدعاءA/78/510
العنوانProgress on the replacement of office blocks A-J at the United Nations Office at Nairobi : report of the Secretary-General
إمكانية الوصولEnglish: A_78_510-EN - PDF ; Español: A_78_510-ES - PDF ; Français: A_78_510-FR - PDF ; Русский: A_78_510-RU - PDF ; العربية: A_78_510-AR - PDF ; 中文: A_78_510-ZH - PDF ;
المؤلفونUN. Secretary-General
معلومات عن جدول الأعمال
A/78/251 134 Proposed programme budget for 2024. UN--BUDGET (2024)
تاريخ[New York] : UN, 5 Oct. 2023
الوصف
36 p. : ill., graphs, tables
ملاحظات
Annexes (p. 29-36): 1. Updated project cost plan -- 2. Evolution of resources in cost plans -- 3. A. Monthly project expenditure as at 31 July 2023, B. Total project expenditure by category as at 31 July 2023 -- 4. Use of the contingency provision (spent and earmarked).
6th annual progress report; submitted pursuant to section XII of General Assembly resolution 77/263 A; provides information on the progress made since the issuance of the previous report (A/77/349).
6th annual progress report; submitted pursuant to section XII of General Assembly resolution 77/263 A; provides information on the progress made since the issuance of the previous report (A/77/349).